Test Procedure

RXin / RXout models · Five continuity checks

Return to Home page

Check your RXin / RXout SDRSwitch with the power disconnected, then with 12 VDC connected, and finally with your radio’s PTT cable. Compare the meter readings for each test with the tables below.

SDRSwitch front panel showing TX, RXin, RXout and ANT BNC ports
Front-panel ports used in all five tests.

Before you start

  • A 12 VDC power supply (11–15 VDC).
  • A multimeter set to the ohms scale.
  • A shorted RCA male test plug with its center contact connected to its outer shell.

Touch the meter probes together. A reading near 0 ohms (often accompanied by a beep) means closed circuit (CC). Separate the probes. OL, infinity or no continuity means open circuit (OC).

For each reading, place one probe on the center pin of each BNC connector named in the table. The enclosure stays closed.

Tests 1–3 · Check the switch on its own

  1. Unpowered. Leave the power supply and all other cables disconnected. Check the four pairs below.
  2. Receive. Connect only 12 VDC and check the same four pairs.
  3. Transmit with the test plug. Leave 12 VDC connected and insert the shorted RCA plug into PTT. Check the four pairs again.
BNC center-pin pair Test 1
Unpowered
Test 2
12 VDC / receive
Test 3
PTT plug shorted
TX to ANT CC OC CC
TX to RXin OC CC OC
ANT to RXout OC CC OC
RXin to RXout OC OC OC

Remove the shorted RCA test plug before continuing.

Tests 4–5 · Check the switch with your radio

  1. Radio in receive. With the shorted RCA plug removed, connect the radio’s compatible PTT cable to the switch’s PTT input. Leave the radio in receive and check the four pairs in the Test 4 column.
  2. Radio PTT asserted. With the radio’s RF output safely separated as described above, key the radio and check the four pairs in the Test 5 column. Release PTT and confirm that the readings return to the Test 4 values.
BNC center-pin pair Test 4
Radio in receive
Test 5
Radio PTT asserted
TX to ANT OC CC
TX to RXin CC OC
ANT to RXout CC OC
RXin to RXout OC OC

How did your switch do?

If your readings match all five columns, the switch passed the continuity checks for power off, receive and transmit. The checks cover continuity only. RF isolation, switching timing and power handling require separate measurements.

If a reading differs, check the port labels, probe contact, power supply, test plug and PTT cable, then repeat that test. If the reading still differs, leave the SDR disconnected and contact Paul before using the setup to transmit.

Make a shorted RCA test plug

  1. Find an RCA cable and disconnect it from all equipment.
  2. Cut off one plug, leaving a few inches of cable attached to it.
  3. Strip back the cable jacket to expose the inner wire and the outer shield or braid.
  4. Strip the insulation from the inner wire and twist its bare copper together with the outer shield or braid.
  5. Wrap the joined wires with electrical tape.
Shorted RCA test plug made from a short length of cable with the wire junction wrapped in electrical tape
Shorted RCA test plug example supplied by W3UJ.

Use this plug only in the switch’s PTT input for Test 3. Remove it before Tests 4 and 5. Do not connect it to the power input or an audio output.

Record your results

Enter CC, OC or your meter reading alongside each expected value. Leave any test you did not complete blank.

Test / state TX to ANT TX to RXin ANT to RXout RXin to RXout
1. Unpowered Expected CC
Expected OC
Expected OC
Expected OC
2. 12 VDC / receive Expected OC
Expected CC
Expected CC
Expected OC
3. PTT plug shorted Expected CC
Expected OC
Expected OC
Expected OC
4. Radio in receive Expected OC
Expected CC
Expected CC
Expected OC
5. Radio PTT asserted Expected CC
Expected OC
Expected OC
Expected OC

Expected readings from the original SDRSwitch procedure by Paul, N2EME. Web procedure and worksheet based on the guide written by W3UJ.